SPLOST Project Description: Judicial Facilities will be constructed at approximately 310,000 square feet of space to provide adequate space for Superior, State, Juvenile, Municipal/Magistrate, Probate, and Juvenile Courts as well as all court related space for Judges and Clerks of each court, Sheriff, District Attorney, Public Defender, Accountability Courts, and other court related functions at an estimated cost of $188,000,000, plus an approximate 500-600 space parking facility at an estimated cost of $12,000,000.
SPLOST Referendum included the issuance of $200,000,000 in General Obligation Bonds to advance the construction of the Judicial Center (Note: All others projects would be pay-as-you-go.)
2021 SPLOST Project Budget = $200,000,000
342,000 Gross Square Feet 18 Courtrooms (5 Shell) 500+ Site Parking
Ryan Pruett
rpruett@columbusga.org
(706) 653-4126
The following courts and departments will be in the Judicial Center.
The total project budget for the Judicial Center is $207,500,000.00. This includes design costs, furniture, fixtures and equipment, project management and other costs. The estimated construction budget is $192,500,000.00.
The Judicial Center is being paid for by SPLOST General Obligation Bonds proceeds which the debt service is funded from the 2021 Special Purpose Local Option Sales Tax (SPLOST). The SPLOST was approved by voters in November 2021 and dedicated $200 million for the new Judicial Center. In addition, City Council authorized the allocation of $7.5 million in reserve funds to add an additional floor in the Judicial Center to provide growth space for the future needs of the occupants.
Yes. The current Government Center will be demolished upon completion of the Judicial Center and the relocation of all offices to the new building. This will provide space for public parking. The demolition is projected to occur in 2026.
Construction is estimated to start in December 2023. The new Judicial Center will be complete in 2026. Following completion of the new Judicial Center, the existing Government Center will be demolished and the remaining sitework will be completed in 2027.
There will be three ways for the public to enter the Judicial Center. The primary entrance will be at the street level on 10th Street. Secondary entrances are available on the south side of the building at grade level and the Plaza level. All three entrances lead to a two-story lobby.
Yes. There will be a surface lot designated for public parking. The surface lot will contain approximately 130 parking spaces with entrances and exits off 1st Avenue and 2nd Avenue on the north side of 9th Street. Additional public parking spaces will be available on the south side of 9th Street in an overflow surface parking lot.
On-street parking on the south side of 10th Street, east side of 1st Avenue, and west side of 2nd Avenue will be eliminated during construction. In addition, 1st Avenue will be modified to be a southbound one-way street. 2nd Avenue will be modified to be a northbound one-way street. 10th Street will have two-way traffic throughout the construction duration.
When the Judicial Center is complete, there will be 13 courtrooms. There will be an additional five shell courtrooms that will not be fully built-out. The building is designed to accommodate over 20 courtrooms in the future if the need arises.
A website and/or social media page will be established to provide ongoing updates and pictures of the progress during construction.
Yes. Prior to the approval of the 2021 Special Purpose Local Option Sales Tax, multiple options were considered for replacement and/or renovation of the Government Center. These options included constructing the Judicial Center on a different location, renovating the existing Government Center, and constructing a new Judicial Center on the current site. Following multiple public meetings and feedback from user groups, City Council approved the option of constructing a new Judicial Center on the existing site.
The renovation of the existing Government Center building would require all user departments to relocate during construction. This relocation is necessary due to the amount of work required on the existing tower to make it code compliant. To comply with the life safety code a full height addition would have to be constructed in addition to replacing all building systems and replacing the entire exterior skin. The time and money associated with finding a temporary courthouse location and renovating that space make the renovation of the existing tower unfavorable.
During the public meetings regarding the SPLOST, this option was favored by the participants and the existing occupants of the building. This site is also the historic location of the courthouse for Columbus.
The escalated construction costs required an alternate site plan to remain within the budget and still provide the programming contemplated by the referendum.
Public Safety Projects will include acquisition and upgraded Police, Fire & Emergency MedicalService, and Sheriff’s Office vehicles and equipment and restoration of 3 Fire Stations,replacement of 1 Fire Station, and renovations of the Public Safety Building and other publicsafety vehicles, equipment, & facility renovations.
test.user@columbusga.org
(706) 225-0000
Resurface parts of the Columbus River Walk from the Trade Center to Oxbow and fromCity Mills to North Highland Dam.